Place Maillardville Community Centre – Earthworks and Shoring

January 2021 – May 2021
Client: Ledcor Construction Group
Project Value: $1,200,000

1200 Cartier Avenue, Coquitlam

Terra Contracting was prequalified and awarded the PMCC Earthworks and Shoring project by Ledcor Construction Group. This project is a high-profile project for City of Coquitlam is located beside a recreational center and residential homes. Therefore, strict safety procedures were followed and met to successfully close out the project.

For this project, Terra’s scope of work consisted of soldier pile installations, bulk excavation and shoring, detail excavations, slab prep, and building perimeter backfill. Working with Ledcor, Terra successfully completed the project on schedule while coordinating work with other trades.

Key Highlights:

  • Excavation depth – 10 m
  • Installation of soldier piles
  • Excavated 10,000m3 of soil
  • Building perimeter backfill