July 2021 – September 2021 Client: City of Vancouver 750 Hornby St, Vancouver, BC In July 2021, Terra was awarded a contract for civil work at Vancouver Art Gallery in downtown Vancouver. Our scope included removing the existing hardscape, installing a new drainage system, and backfilling and grading the entrance of the Vancouver Art Gallery. […]

The Oaks Civil Upgrade for BC Hydro, Telus, Shaw

July 10, 2024

March 2021 – March 2022 Client: Axiom Builders Inc. 702 – 730 Clarke Road, Coquitlam, BC In the first quarter of 2021, Terra was awarded the Oaks civilupgrade for all the new BC Hydro, Telus, and Shaw work. This project involved 4 phases of work and was a critical task toobtain occupancy and power for […]

Place Maillardville Community Centre – Offsite and Onsite Civil Works

July 10, 2024

August 2021 – May 2022 Client: Ledcor Construction Group Project Value: $1,100,000 1200 Cartier Avenue, Coquitlam Terra Contracting was prequalified and awarded the PMCCEarthworks and Shoring project by Ledcor Construction Group.This project is a high-profile project for City of Coquitlam is locatedbeside a recreational center and residential homes. Therefore,strict safety procedures were followed and met […]

Canadian Pacific Railway – Vancouver Intermodal Facility Lot 1 Truck Chasses Capacity Expansion

July 10, 2024

February 2021 – July 2021 Client: Canadian Pacific Railway Project Value: $1,500,000 17900 Kennedy Rd, Pitt Meadows Subcontracted by Lafarge Canada, Terra Contracting was awardedwith the installation of the drainage system for the CP VIF Lot. The drainage system involved multiple oil-grit separators,manholes, catch basins, and headwall. Over 500m of reinforcedconcrete pipe was installed along […]

E15 – Soil Improvement & Sheetpile Walls

July 10, 2024

November 2021 – November 2022 Client: Urban One Builders Project Value: 2.5 Million 320 East 15th Ave, Vancouver The challenging site conditions, characterized by heavy ground water seepage and highly compressible native materials such as peat and silt, required the removal of all unsuitable materials thatcould not support building loads. Terra’s proposed solution involved the […]

137 East 37th

July 10, 2024

ADDRESS: 137 East 37th Avenue LOCATION: VANCOUVER, BC

Westbury Development

July 10, 2024

April – August 2020 Client: Gryphon Development Project Value: $250,000 Project Name: Westbury Development (4066 Macdonald Street, Vancouver)

Torino Pinnacle (Phase 2) Offsite Civil

July 10, 2024

October – December 2020 Project Owner: Pinnacle International/Mondiale Development Project Value: $420,000