- Sapperton Ground ImprovementDecember 2019 – August 2020 Client: Canadian Pacific Railway Company Project Value: 7.6 million A design build contract awarded by CP Rail, with track expansion work up to 3 Kilometers Long. The track expansion crossed multiple Ministry Transportation overpasses, and Trans mountain utility crossing. The scope of work included the design and construction of ground improvement using CMC ...Read more
- BC Housing Projects2017-2020 Client: Horizon North Logistics Inc Project Value: 2.2 million Terra Contracting was awarded multiple contracts to complete site preparation and site services at various Housing sites in the City of Vancouver. Scope of work includes onsite and offsite site services with sanitary/storm/water tie-ins; site preparation; retaining wall and backfill; and hardscape/landscape. All the project sites demanded short construction ...Read more
- Lower Mainland Intermediate Pressure System Upgrade ProjectOctober 2017 – April 2018 Client: FortisBC Energy Inc. Project Value: 1.9 million The project consisted in locating and exposing of undergroundutilities at specified crossing locations throughout Coquitlam,Burnaby and Vancouver. Over 250 existing underground utilitieswere conducted along a stretch of 22km. Work inclusive ofhydro-excavation and machine excavation, survey backfill andfull restoration to existing conditions and in accordance withMunicipal ...Read more
- Boyd Street, Wood Street, and Johnston Street Storm Network UpgradesOctober 2019 – November 2019 Client: City of New Westminster Project Value: 1.2 million Aplin and Martin as the consulting engineer, Terra was awarded the project by City of New West in the summer of 2019. Despite the tight project schedule to ensure canal capacity was improved before the fall season, Terra was able to complete the entire ...Read more
- The Heights – Charland Avenue, CoquitlamMay 2019 – December 2019 Client: Allaire Construction Inc. Project Value: 1.0 million Charland Avenue, Coquitlam, BC Terra Contracting was awarded the offsite civil contract for The Heights development by Allaire Construction. For this project, Terra installed 140 m of new water main connection from the development site to the intersection of Austin Avenue and Blue Mountain Street in the ...Read more
- Beachborough Offsite Civil ProjectSeptember 2018 – April 2020 Client: Allaire Construction Inc. Project Value: $1,200,000 14034 North Bluff Road, White Rock Terra Contracting was awarded the offsite civil work for the Beachborough development located in the City of White Rock by Allaire Construction. This project involved Terra installing 110 m of new water main along the intersection of North Bluff Road and Nichol ...Read more
- Port Moody Cascade Capacity Expansion Project – Culvert ExtensionsFebruary – April 2020 Client: Canadian Pacific Railway The Cascade track expansion project is located near Suncor plant along the Burrard Inlet. The track expansion runs 12km total along the most sensitive part of Burrard Inlet. Terra was tasked to complete all culvert realignment and extension as part of the track expansion. With strategic water management, and siltation ...Read more
- Port Coquitlam Yard Lagoon Decommissioning And Stormwater Infrastructure UpgradeDecember 2019 – April 2020 Client: Canadian Pacific Railway Project Value: 0.7 Million As a direct contractor to CP, Terra is E-Rail Safe and ISNet world certified. The two certifications allow contractors to exemplify the ability to conduct work in a safe, environmental compliant, and systematic way. The project started in fall of 2019, and the weather posed severe ...Read more
- University Of British Columbia Infrastructure Project: The Counselling Service Civil WorksSeptember 2019 – April 2020 Client: The University of British Columbia The project was awarded to Terra by the UBC Properties Trust. Under strict time constraint, Terra was able to accommodate the team from Metric Modular to install site services for a modular facility while working around other subcontractors around the area. Traffic control was also a ...Read more
- Westbury DevelopmentApril 2020 – September 2020 Client: Gryphon Development Project Value: $250,000 4066 Macdonald Street, Vancouver, BC Terra Contracting was awarded the Westbury Offsite Civiland Roadworks project by Kindred Construction and GryphonDevelopment. For this project, extensive communication andcoordination were required to work efficiently and safely withother trades on site due to the limited working space. Terra’s scopeof work consisted of ...Read more